A refit (refurbishment) means carrying out a boat's structural, timber, coating, sealing and hardware work within one plan. Finishing the paint and then doing joinery or bonding brings back paint dust and damage. That is why the most valuable things in a refit are the right sequence and a written scope. When each job is done directly affects the quality and cost of the result.
In short:
- A refit starts with a survey; the scope list is written in order of priority: structure and safety, systems, then aesthetics.
- General work order: removal, structure, joinery, paint and varnish, sealing and refitting, antifouling, relaunch.
- Dusty and dirty work comes before paint and varnish; delicate fitting work is left until last.
- A budget and time contingency should be set aside for unexpected work; every boat that is opened up reveals new findings.
How is a yacht refit planned?#
- Survey
Hull, deck, timber, moisture, systems and hardware are inspected. Findings are recorded with photos and measurements.
- Scope list
Work is written item by item: essential, recommended and optional work are separated.
- Priority and budget
Safety and structure come first. A contingency is set aside for unexpected work.
- Schedule
Drying and curing times, weather and time ashore are taken into account.
- Approval and records
Scope changes require written approval and progress is photographed.
For details of the survey and scope list, see our refit survey and scope of work guide.
The right order of work in a refit#
In a refit, sequence determines cost as much as quality. Work that creates dust and moisture comes first; delicate and clean work comes later.
- Survey: scope
- Removal: hardware, paint
- Structure: laminate, osmosis
- Timber: joinery
- Coatings: paint, varnish
- Refitting: sealing
Antifouling and relaunch come last.
| Stage | Work | Guide |
|---|---|---|
| Structure | Crack, hole and laminate repair, moisture and osmosis | Fibreglass repair, Boat osmosis |
| Joinery | Interior, teak deck, hatches and doors | Boat joinery |
| Surface correction | Gelcoat repair, fairing, sanding | Gelcoat repair |
| Coatings | Topside paint, varnish, deck | Yacht painting, Boat painting, Boat varnish |
| Sealing and refitting | Windows, seams, under-hardware | Sikaflex applications |
| Underwater and relaunch | Antifouling, anodes, propeller | Antifouling |
- 1CoatingsTopside paint, varnish, deck; antifouling below the waterline
- 2Surface correctionGelcoat repair, fairing, sanding
- 3Base: structure and laminateCrack, hole and laminate repair, moisture and osmosis
No layer is applied until the work beneath it is finished and checked; values come from the product data sheet.
Where we work on the boat during a refit#
Tap a number or an area in the list.
Refit management: what to watch for#
- Written scope: what will and will not be done must be clear.
- Change approval: new findings and extra work must be approved in writing.
- Work log: photos, measurements and products used must be recorded.
- Other trades: electrical and mechanical work must be built into the work order, and jobs that overlap in the same area planned in advance.
- Quality checkpoints: inspections before primer, topcoat and refitting.
Common refit mistakes#
- Finishing dusty work before paint and varnish
- Writing the scope item by item
- Setting aside a contingency for unexpected work
- Starting with a survey
- Respecting drying and curing times
- Comparing quotations item by item
- Breaking the sequence: sanding or dusty work after painting
- Not writing the scope and losing the budget to piecemeal additions
- No contingency for unexpected work
- Starting without a survey
- Cutting drying and curing times short
- Not comparing quotations item by item
Detailed guides on refit topics#
Separate step-by-step, illustrated guides for each work item:
- Moisture measurement, drying and surveys: How is moisture measured on a boat? Measuring points, types of moisture meter, drying follow-up, osmosis and cored deck moisture, post-damage surveys and reporting.
- Haul-out and relaunch: How are haul-out and relaunch planned? Sling points, cradle pads, boat support, prior checks, antifouling timing and launch checklist.
- Refit survey and scope of work: How is a pre-refit survey carried out and a scope list prepared? Priority pyramid, documenting findings, itemised budget, unexpected work and quote comparison.
- Removal, refitting and work log: How are hardware removal, labelling, storage, refitting, work order coordination, photo work log and handover file managed in a refit?
- Boat painting cost and price: What determines the price of boat and yacht painting? Length, surface condition, preparation, product system, number of coats, time ashore, quotation items and low-price warnings.
- Seasonal maintenance and winterising: How is end-of-season and start-of-season maintenance done? Washing, salt removal, moisture control, ventilation, varnish and timber protection, seam checks, antifouling and launch checklist.
Yacht refit FAQ#
How long does a refit take?
It depends on the scope, weather and drying times. It ranges from weeks to months; a firm schedule is given after the survey and scope list.
Refit or a new boat?
The structural condition and value of the boat decide. On a structurally sound boat a refit can often be more economical than buying new, but this depends on the size of the boat and the scope.
Does the boat stay ashore during a refit?
Yes, the boat is hauled out for work such as painting, structural repair and antifouling. Time ashore also determines yard and marina costs.
Can a refit be done in phases?
Yes. Priority work (structure, sealing, underwater) can be done in the first season and aesthetic work in later seasons, but the sequence must be maintained.
How is a refit budget planned?
Each item on the scope list is priced, then a contingency for unexpected work is added. Compare quotations item by item, not just by the total figure.
What determines the price of a boat refit?
Boat length, structural condition, the work items in the scope, product systems, the amount of preparation and time ashore. A firm price is given in writing, item by item, after the survey.
When should I consider a refit?
A single-plan refit makes sense when several jobs come together, such as structural doubts, widespread leaks and worn coatings and timber. An early survey is recommended so that time ashore can be planned properly.