The most common problem in refit projects is an unclear scope. A job that starts with "let us paint it and do a bit of woodwork" grows halfway through as new findings appear, and the budget and schedule slip. A survey and a written scope of work set the limits of the job, separate the priorities and make quotations comparable. The survey and the written scope decide what will be done, in what order and how long it will take.
In short:
- Safety and structure come first, then systems, then coatings, and finally comfort and aesthetics.
- The scope list is written item by item; essential, recommended and optional work are separated.
- A budget and time contingency is set aside for unexpected work.
- Any scope changes require written approval.
The refit priority pyramid: structure first, looks last#
- 1Comfort and aestheticsCan be split into phases to suit the budget
- 2Coatings and appearancePaint, varnish
- 3Systems and hardwareDeck hardware, fittings and other systems
- 4Base: safety and structureLaminate, moisture, deck, sealing; cannot be postponed
From bottom to top: foundations first, appearance last. Aesthetic work does not start until structural problems are solved.
The pyramid shows what should be done first on a limited budget. Structural and safety work cannot be postponed, whereas aesthetic work can be split into phases. The scope list should reflect this priority.
What does a boat refit survey inspect?#
Tap a number or an area in the list.
For moisture and laminate findings, see our guides on moisture measurement, drying and surveys and boat osmosis.
How is a refit scope of work prepared?#
- Inspect: photos and measurements
- Record: findings
- Write: work items
- Classify: priority
- Price: item by item
- Approve: in writing
No work starts without a written scope.
- On-site inspection
The boat is inspected inside and out; photos and measurements are taken.
- Recording findings
Each finding is recorded with a photo, description and location.
- Writing work items
For each finding, the work, the method and the product are written down.
- Priority classification
Work is separated into essential, recommended and optional.
- Price and time
Each item is given a price and duration; a contingency for unexpected work is added.
- Sequencing
Work is placed in the right order; drying and curing times are built into the schedule.
- Approval
The scope is approved in writing; any changes require written approval.
For the order in which an approved scope is carried out, see refit and refurbishment; for removal and documentation, see removal, refitting and work log.
Comparing yacht refit quotations#
| Criterion | What to look at | Why it matters |
|---|---|---|
| Scope | Which work is included and which is excluded | A missing item becomes an extra cost later |
| Product system | Brand, product, number of coats | Determines quality and durability |
| Preparation | Removal, sanding, repair work | Determines most of the result |
| Duration | Allowance for drying and curing | A realistic schedule |
| Warranty and records | Handover record and aftercare advice | Reference for the future |
Common mistakes in refit surveys#
- Starting with a survey
- Writing the scope item by item
- Comparing quotations item by item
- Setting aside a contingency for unexpected work
- Solving structure and safety first
- Getting changes approved in writing
- Starting without a survey
- Leaving the scope verbal
- Comparing quotations on total price only
- No contingency for unexpected work
- Prioritising aesthetics and postponing structure
- Not getting changes approved in writing
Refit survey FAQ#
Is a survey needed for every refit?
It may not be needed for minor maintenance, but in a full refurbishment knowing the hull, moisture and structural condition sets the scope and budget correctly. If there is any structural doubt, it is essential.
What goes into a scope list?
Work item, description, product/material, quantity, priority and estimated duration. The parts of the job that will not be done are also stated.
How much contingency should be set aside for unexpected work?
It depends on the age and condition of the boat; it is usually set as a reasonable percentage of the total budget. As the survey clarifies the scope, the contingency shrinks.
How do I compare quotations?
Compare item by item rather than by the total figure. Look at the product system, number of coats, preparation, and what is and is not included.
Can a refit be done in phases?
Yes; safety and structure first, then coatings and comfort work can be done in phases. The order and compatibility must be maintained.
What determines the price of a refit survey and scope list?
Boat length, the number of areas to be inspected, the measurements required and whether the boat is ashore or afloat. A firm figure is given in writing once your request has been reviewed.
How long do a survey and scope list take?
It depends on the size of the boat, access and the measurements required. We confirm an estimated timeline in writing after your survey request.