Refit and Maintenance
Pre-Refit Condition Survey: Inspection and Measurement Methods
The quality of a refit is limited by the quality of the data gathered before the first sheet of abrasive touches the hull. The condition survey is the stage that turns assumption into information, and information into scope.
Short answer
A pre-refit condition survey is the zone-by-zone assessment of a yacht’s hull, coatings, deck and systems by non-destructive methods such as visual inspection, tap testing, moisture measurement, ultrasonic thickness gauging and adhesion testing, with every finding recorded by location, value and photograph.
Key points
- The condition survey is the only objective basis for the scope and budget of a refit.
- No single method is sufficient; methods must corroborate one another.
- Moisture and thickness readings should be taken on a grid and recorded with their positions.
- The report does not merely list findings; it ranks them and links each to a proposed scope.
Purpose and extent of the condition survey#
The condition survey is the marine counterpart of diagnosis in medicine. Before treatment begins, it establishes what the problem is, how far it has spread and in what order it should be addressed. Omitting or skimping this stage in a refit has two typical outcomes: either the scope is drawn too wide and the owner pays for work the yacht did not need, or it is drawn too narrow and the real problem emerges during dismantling, at the moment when schedule and budget are most fragile.
The governing principle: methods that corroborate one another#
In non-destructive examination no method is conclusive on its own. When a moisture meter shows a high reading, only a second observation can tell whether it stems from water in the laminate, metal in the antifouling or a water tank on the inside. A sound condition survey therefore rests on at least three sources of information that test one another: what is seen, what is measured with instruments and what is learned from the vessel’s history.
| Method | What it reveals | Limitation |
|---|---|---|
| Visual inspection | Cracks, blisters, discolouration, deformation | Does not show what lies beneath the surface |
| Tap testing | Delamination, voids, degraded core | Interpretation depends on experience |
| Moisture measurement | Relative moisture in laminate and timber | Affected by metal, salt and wet surfaces |
| Ultrasonic thickness gauging | Remaining thickness of steel and aluminium plate | Requires clean surface and calibration |
| Dry film thickness measurement | Total coating thickness on metal | Special probes needed on fibreglass |
| Adhesion testing | Bond of coating to substrate | Causes minor local damage |
| Thermal imaging | Wet core, thermal bridges | Requires a temperature difference |
Visual inspection: looking systematically#
Visual inspection is the oldest method and still the most productive, provided it follows a pattern rather than a casual walk round. The hull is scanned in bands from bow to stern and from keel to gunwale. A strong light held at a low angle reveals undulations, the edges of old repairs and blisters that the unaided eye would miss.
Tap testing#
When a surface is struck with a light plastic or phenolic-headed hammer, sound laminate gives a crisp, clear note, whereas a delaminated area or one with a wet core sounds dull and dead. The method appears simple but depends on two conditions: the surface must be covered at regular intervals, and the boundary of any suspect area must be marked. A finding whose boundary is not drawn cannot be converted into square metres when the scope is written.
Moisture measurement: pattern rather than value#
Moisture meters detect changes in the electrical properties of the laminate, and most report on a relative scale. A single number therefore has limited absolute meaning; what matters is its distribution over the hull and its change over time. For readings to be reliable, the following conditions should be met.
- After haul-out the surface is allowed to dry; readings taken immediately after washing are misleading.
- Measurement points are laid out on a grid and numbered on the hull.
- A comparison reading is taken above the waterline in an area known to be dry.
- Points where a tank, bilge water or metal reinforcement lies on the inside are noted separately.
- Air temperature and relative humidity are recorded at the time of measurement.
Copper in the antifouling and salt on the surface can raise readings. In suspect areas, removing the coating from a small patch and measuring directly on the gelcoat or laminate eliminates false positives. The interpretation of moisture readings and the decision to treat are discussed in detail in the article on osmosis treatment.
- Underwater measurement grid: moisture readings taken at numbered points
- Topside comparison point: reference value from a dry area
- Hull-to-keel joint: check for opening and rust staining
- Rudder blade and stock: tap test and void check
- Through-hull fittings and seacocks: corrosion and sealing
- Deck hardware bedding: moisture and delamination in the core
Thickness gauging on metal hulls#
On steel and aluminium hulls, the amount of material lost to corrosion is determined by ultrasonic thickness gauging. The instrument measures the time taken by a sound pulse sent from one face of the plate to return from the other; the remaining thickness is thus read without access to the inside. Measurement points are chosen to a plan: the waterline belt, bilges, tank bottoms, fore and aft peaks and the areas around welds take priority.
Two forms of deterioration are assessed separately. General wastage is an even loss of thickness over a wide area and is tracked by the average value. Pitting is corrosion that deepens locally while the surrounding plate remains sound; here the governing figure is not the average but the depth of the deepest pit. The permissible loss of thickness is determined by the rules to which the vessel was built and, where applicable, by the criteria of her classification society. The subject is developed in the article on steel hull refits.
Assessing the coatings#
Whether new coats can be applied over the existing paint system is one of the decisions that most affects a refit budget. It rests on three questions: does the coating adhere to the substrate, is the total thickness at a level that can carry further coats, and is the old system chemically compatible with the new product?
Adhesion is tested by a cross-cut or pull-off test. Total thickness on a metal hull is measured with magnetic or eddy-current instruments. For compatibility, a common yard method is to hold a cloth wetted with the new product’s thinner against a small area and observe whether the old film softens. A negative answer to any of the three questions indicates that the coating must be removed.
Recording findings and reporting#
A measurement is worth no more than its record. A good condition survey report contains the following elements.
- Vessel identity
- Model, year of build, hull material, known repair history
- Measurement conditions
- Date, air temperature, relative humidity, time ashore
- Measurement plan
- Grid diagram and numbered points
- Findings
- Location, measured value, photograph and brief description
- Prioritisation
- Safety, structural, protective and cosmetic classes
- Proposed scope
- Recommended work and options for each finding
- Uncertainties
- Points to be clarified after dismantling
From survey to scope#
Once the report is complete, each finding is linked to a work item, and each work item to a quantity and an acceptance criterion. For example, the finding “dull-sounding area of 0.6 square metres on the starboard bow shoulder” becomes the work item “open the laminate in the affected area, dry, re-laminate with a 12:1 scarf ratio and verify by tap test”. This conversion is the raw material of the work breakdown and schedule.
Conclusion#
The condition survey is the least expensive stage of a refit and the one that saves the most. Corroboration between methods, recording readings with their positions and ranking the findings determine the reliability of every later decision. A scope written for an unmeasured vessel is, however well intended, an assumption.
How long does a condition survey take?
It depends on the size of the yacht and the extent of the survey. On a mid-size yacht, hull and deck measurements are usually completed within one or two days; detailed inspection of the systems extends the time.
Can a condition survey be carried out afloat?
The superstructure, deck, interior and systems can be inspected afloat. Assessment of the underwater hull, the keel joint and the stern gear requires the yacht to be hauled out.
Does a high moisture reading mean osmosis?
No. A high reading only shows that closer examination is needed. Diagnosis is made by considering together the distribution of readings, the presence of blisters, the nature of the blister fluid and the behaviour of the hull during drying.
Was this guide helpful?
Thank you! Your feedback has been saved.
Guide content is for general information; in practice, the current technical data sheet of the product applies.
Keep reading
Related guides
Tank Inspection, Maintenance and Repair: Holiday Testing, Thickness Measurement and Records
Inspection, thickness measurement, holiday testing, repair approaches and records for steel boat tanks, summarised from source accounts with their limits.
10 min read Refit and MaintenanceGrey Water, Black Water and Shower Tanks: Corrosion, Lining and Design
Why grey, black and shower tanks on steel boats corrode, what an internal lining does and design details, summarised from source accounts.
11 min read Refit and MaintenanceDrinking-Water Tank Epoxy Lining: Selection, Stripe Coat, Cure and Disinfection
Product documents, stripe coat, cure, flushing and disinfection steps in epoxy lining of drinking-water tanks, summarised from source accounts with their limits.
11 min read